Published: Jan. 14, 2013

Construction on campus utilities in the vicinity of the Center for Community, Leeds School of Business, and Regent Administrative Center will resume later this week. The construction activity, which is part of a larger project to provide efficient heating and cooling while significantly reducing the university鈥檚 carbon emissions, was delayed in December 2012 due to unexpected circumstances. A directional boring followed by a pipe pull is scheduled for early February, with construction in the area expected to wrap up by mid-February.听

The patience of the campus community is greatly appreciated during this temporary disruption. Please exercise caution in the area and follow all construction signs. For construction information and daily updates, please visit the project page at the link below (please note that it is not necessary to be a Facebook member to view the page.)